Tutorial Step 13: Level Resources
Two tasks are assigned to use the resource Me and the resource Glue at the same time.
Click the Level button
in the toolbar, then deselect the Don't schedule any task before date checkbox and click OK.
The second task moves to avoid the resource usage conflict.